Afula: BOT tender for a sorting transfer station
A BOT tender for building a sorting transfer station, the first of its kind – from planning and permits to operation. The station sorts 1,000 tons of waste per day.
1,000tons of waste sorted per day
- Location
- Afula
- Area
- Waste tenders
Background
Preparation of a BOT tender for building a sorting transfer station by the contractors bidding in the tender, including planning, regulatory approvals and support for the project from start to finish.
The challenge
The first station of its kind, sorting at a rate of 25%.
The need
The State of Israel adopted a policy of reducing waste landfilling, because there are not enough land reserves for landfills – and in order to make greater use of non-degradable materials for recycling.
What we did
- Writing the entire tender.
- Preparing construction plans.
- Environmental impact assessments.
- Traffic impact assessments.
- Supporting the winning contractor, from construction to operation.
The solution
The plant is up and running, sorting the waste into many components.
The bottom line
Results
- 1,000tons of waste sorted per day
- 25%sorting rate at the station
What we did in the project
Services we provided
Waste tenders
Defining the authority's needs, quantities, equipment and service level, through to a professional, precise tender.
Transfer stations
Consulting, planning and project management for transfer and sorting stations.
Environmental surveys
Professional environmental surveys as a basis for decisions and planning.